Wednesday, March 4, 2009

Burj Dubai Construction Progress and Timeline



Click on the picture to enlarge

September 2004: Contractors from Emaar begin the construction of the future world tallest building.

February 2007: Surpasses the Sears Tower with height of 500m.

May 2007: Surpasses the 449.2 m (1,474 ft) to which concrete was pumped during the construction of Taipei 101.

July 2007: Surpasses Taipei 101, with height of 509.2 m (1,671 ft).

August 2007: Surpasses Sears Tower antenna, with height of 527.3 m (1,730 ft).

September 2007: Surpasses Ostankino Tower Moscow with height of 540 m (1,772 ft) .

September 2007: Surpasses CN Towe in Toronto with height of 555.3 m (1,822 ft).

April 2008: Surpasses the KVLY-TV Mast with height of At 629 m (2,064 ft).

June 2008: Burj Dubai's height is now over 636 m (2,087 ft) being announced by Emmar properties.

September 2008: Surpasses the previous record-holder- of world tallest building the Warsaw Radio Mast in Konstantynów with height of 688 m (2,257 ft) , Poland.

January 2009: Current height of 818 m (2,684 ft).

The final height is still a clue as Emaar did not announce about it but it's confirmed that the Burj Dubai tallest man made tower will open on the 9 sept 2009 coincidence with the launch of Dubai Metro.